Which one of the following statements does NOT accurately describe a good project schedule?


A) Project schedules define specific task objectives.
B) Project schedules do not specify resource requirements.
C) Project schedules assign priorities.
D) Project schedules assign activities to be accomplished.
E) Project schedules specify dates and timetables for the activities.