A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results:
What is the standard time for this task if the employee worked at a 25 percent faster pace than average and an allowance of 20 percent of the workday is used?
A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds
Correct Answer:
Verified
Q165: A methods and measurements analyst for Timepiece,
Q166: The design of work systems typically involves:
(I)work
Q167: The owner of Kat Motel wants to
Q168: Methods analysis and motion study techniques develop
Q169: A methods and measurements analyst for Timepiece,
Q171: A methods and measurement analyst wants to
Q172: A methods and measurements analyst for Timepiece,
Q173: The owner of Kat Motel wants to
Q174: A methods and measurements analyst needs to
Q175: A methods and measurements analyst needs to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents