QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:
For output to equal forecasted demand, what should be the actual cycle time for this production?
A) 32 seconds
B) 38 seconds
C) 40 seconds
D) 76 seconds
E) 152 seconds
Correct Answer:
Verified
Q114: The maker of the world-famous Chocolate Chip
Q115: A company needs to locate three departments
Q116: A company needs to locate three departments
Q117: A company needs to locate three departments
Q118: The maker of the world-famous Chocolate Chip
Q120: A company needs to rebalance a product
Q121: Although they do not guarantee optimal solutions,
Q122: 3D printing is also known by this
Q123: Which of the following does not reflect
Q124: Which of the following does not reflect
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents