The operations manager for the Blue Moon Brewing Co. produces two beers: Lite (L) and Dark (D) . Two of his resources are constrained: production time, which is limited to 8 hours (480 minutes) per day; and malt extract (one of his ingredients) , of which he can get only 675 gallons each day. To produce a keg of Lite beer requires 2 minutes of time and 5 gallons of malt extract, while each keg of Dark beer needs 4 minutes of time and 3 gallons of malt extract. Profits for Lite beer are $3.00 per keg, and profits for Dark beer are $2.00 per keg.
For the production combination of 135 Lite and 0 Dark, which resource is slack (not fully used) ?
A) time (only)
B) malt extract (only)
C) both time and malt extract
D) neither time nor malt extract
E) cannot be determined exactly
Correct Answer:
Verified
Q68: An electronics firm produces two models of
Q69: The owner of Crackers, Inc., produces two
Q70: The operations manager for the Blue Moon
Q71: A local bagel shop produces two products:
Q72: A local bagel shop produces two products:
Q74: The production planner for a private label
Q75: The production planner for a private label
Q76: The production planner for a private label
Q77: The production planner for a private label
Q78: An electronics firm produces two models of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents