At Which Point Does Crashing of a Project Cease

Question 80

Multiple Choice

At which point does crashing of a project cease?


A) when the project is completed
B) when no additional crashing is possible
C) when the cost to crash equals or exceeds the benefit of crashing
D) when the project is one-half completed
E) when the team has been disbanded

Correct Answer: