What is the basic process for calculating the event late time for an event in the middle of a network diagram?
A) Add the duration of the preceding activity (to the left) to its early time
B) Subtract the duration of the preceding activity (to the left) to its early time
C) Add the duration of the following activity (to the right) to its early time
D) Subtract the duration of the following activity (to the right) to its early time
Correct Answer:
Verified
Q1: Which of the following statements about float
Q3: Which of the following statements concerning events
Q4: Consider the following network diagram [insert network
Q5: Consider the event in a network diagram
Q6: Which of the following options is the
Q7: What is a precedence table?
A) A tabular
Q8: Which statement concerning dummy activities is NOT
Q9: Which of the following options is the
Q10: How might the earliest activity finish time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents