A construction firm in Oman is running two projects (A and B) . The probability that A will complete on time is 0.85 and the probability that B will complete on time is 0.65. What is the chance that only one of these projects will complete on time (2 decimal places) ?
A) 0.35
B) 0.36
C) 0.37
D) 0.38