Larkin Industries manufactures several lines of decorative and functional metal items. The most recent order has been for 1200 door lock units for an apartment complex developer. The sales and production departments must work together to determine delivery schedules. Each lock unit consists of three components: the knob and face plate, the actual lock itself, and a set of two keys. Although the processes used in the manufacture of the three components vary, there are three areas where the production manager is concerned about the availability of resources. These three areas, their usage by the three components, and their availability are detailed in the table.
A quick look at the amounts available confirms that Larkin does not have the resources to fill this contract. A subcontractor, who can make an unlimited number of each of the three components, quotes the prices below.
Develop a linear programming model that would tell Larkin how to fill the order for 1200 lock sets at the minimum cost.
Correct Answer:
Verified
Q2: A decision maker would be wise to
Q5: Using minutes as the unit of measurement
Q15: Compared to the problems in the textbook,real-world
Q24: An ad campaign for a new snack
Q25: For the multiperiod production scheduling problem in
Q27: FarmFresh Foods manufactures a snack mix called
Q30: The Tots Toys Company is trying to
Q32: G and P Manufacturing would like to
Q34: A company makes two products, A and
Q56: Evans Enterprises has bought a prime parcel
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents