​The Creation of a Work Breakdown Structure Is Helpful in the Development

Question 59

Multiple Choice

​The creation of a work breakdown structure is helpful in the development of what?


A) Software testing plan.
B) Project iteration schedule.​
C) Detailed work schedule.
D) ​Detailed effort estimates of work tasks.

Correct Answer: