In , the project manager does not have complete authority over the project team, because administratively the members still work for their respective functional managers.
A) an autonomous project organisational structure
B) a functional organisational structure
C) a matrix organisational structure
D) a project management office
Correct Answer:
Verified
Q28: is found primarily in companies that are
Q29: is kind of a hybrid; a mix
Q30: As projects wind down and are completed
Q31: In , in most cases if an
Q32: In , each project is operated like
Q34: Companies with are in the projects business;
Q35: In , there is little opportunity for
Q36: In , one of the team members
Q37: In , projects are continually being completed
Q38: can be cost-inefficient both for individual projects