The is the amount that was budgeted to achieve the work that was scheduled to be performed up to that point in time.
A) total budgeted cost (TBC)
B) cumulative actual cost (CAC)
C) cumulative budgeted cost (CBC)
D) cumulative earned value (CEV)
Correct Answer:
Verified
Q21: A cost is determined for each period,
Q22: Allocating total project costs for the various
Q24: Large projects would have charge codes for
Q25: Travel costs in the project costs estimate
Q26: Contingency costs in the project costs estimate,
Q28: To keep track of _, it's necessary
Q29: Once a total budgeted cost has been
Q30: It is important to use the _
Q31: The project cost estimate is allocated to