If an organisation or subcontractor has performed similar projects in the past and has kept records of how long specific activities actually took, these historical data
A) can be used as a guide in estimating the durations of similar activities for future projects.
B) have no value for the current project.
C) should be stored in files.
D) should be shared with the customer after the contract is signed to show that the contractor can complete the project.
Correct Answer:
Verified
Q24: A change in the estimated duration of
Q26: Having the person who will be responsible
Q28: It is necessary to monitor the progress
Q29: An updated project schedule can be generated
Q33: The estimated duration for each activity must
Q35: It is important to know what types
Q36: Throughout a project, changes may occur that
Q37: When estimating the types and quantities of
Q40: Project management is a proactive approach to
Q60: Calculate the earliest finish for Task B
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents