Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated
A) by subtracting the activity's estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - estimated duration.
B) by subtracting the activity's estimated duration to the activity's earliest start time: EF = ES • estimated duration.
C) by adding the activity's estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + estimated duration.
D) by adding the activity's estimated duration to the activity's earliest start time: EF = ES + estimated duration.
Correct Answer:
Verified
Q24: A change in the estimated duration of
Q40: Project management is a proactive approach to
Q41: In order to establish a basis from
Q42: Throughout the performance of the project, some
Q43: Calculate the latest finish for Task D
Q46: The earliest start time for a specific
Q47: Latest finish time (LF)is the latest time
Q50: Calculate the earliest start for Task D
Q57: Calculate the earliest start for Task B
Q60: Calculate the earliest finish for Task B
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents