Snodgrass and Payne Limited's materials budget for April 20X4 comprised 6 metres of raw material at a standard cost of £2.30 per metre for each unit produced and sold.Actual sales and production for the month was 680 units.The outturn was that 6.20 metres of raw material were used for each unit at a cost of £2.40 per metre. What was the materials quantity variance for April 20X4?


A) £734.40 (F)
B) £312.80 (A)
C) £312.80 (F)
D) £734.40 (A)