A/An _____ System Takes a Period-By-Period Set of Master Production

Question 44

Multiple Choice

A/An _____ system takes a period-by-period set of master production schedule requirements (anticipated or booked customer orders) and produces a time-phased set of material, component, and subassembly requirements timed to support an expected build schedule.


A) kanban
B) DRP
C) just-in-time
D) perfect order
E) MRP

Correct Answer: