Users apply _____ to projects where there is a single known time (known as a deterministic time) for each activity with no variance, while _____ applies to projects where time estimates are variable or uncertain.
A) Make-buy analysis….CPM
B) PERT….CPM
C) Post-completion analysis….PERT
D) CPM…PERT
E) PERT….TCO
Correct Answer:
Verified