On a day-to-day basis, works orders intended to be issued from the MRP will often have a variable effect on the loading of particular machines or individual workers. Which plans project
This load ahead?
A) Organisational work plans
B) Rough cut capacity plans
C) Capacity requirements plans
D) Resource requirements plans
Correct Answer:
Verified
Q43: A product file contains a unique standard
Q44: A simplified diagram showing parts required to
Q45: The finished product is said to be
Q46: Parts that go into sub-assemblies are at
Q47: The components required for a product are
Q48: MRP systems that started to include feedback-loops
Q49: The MRP netting process involves:
A) Moving from
Q50: Considering product structure shape, the more components
Q51: Rough cut capacity plans are static level
Q53: Which of the following is considered a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents