In an operating system, processes A / B / C have the following maximum designed capacity: A = 1600 units / B = 1550 units / C = 1800 units. If the actual measured output is 1400 units, what is the
System efficiency?
A) 75%
B) 85%
C) 90%
D) 95%
E) 105%
Correct Answer:
Verified