A Pumped Hydroelectric Facility Has an Upper Reservoir with an Area

Question 13

Essay

A pumped hydroelectric facility has an upper reservoir with an area of 2 km2\mathrm { km } ^ { 2 } and an average depth of 40 m40 \mathrm {~m} . The average head is 200 m200 \mathrm {~m} . The design requires that the upper reservoir can be filled from the lower reservoir in a period of 8 hours.
(a) What is the electrical power required by the pumps? Assume a pumping efficiency of 85%85 \% .
(b) What is the flow rate (in m3/s\mathrm { m } ^ { 3 } / \mathrm { s } ) of water being pumped to the upper reservoir?

Correct Answer:

verifed

Verified

(a) The en...