Which statement is true of Critical Path Method (CPM) ?
A) Activities on the critical path take the shortest time to be completed.
B) It determines the critical path for the completion of a series of interrelated activities.
C) Activities that are on the critical path are flexible and can be delayed without delaying a project.
D) A delay in the activities of a project does not affect the scheduled delivery of the project.
Correct Answer:
Verified
Q36: Finding out what users do and how
Q37: In the context of information systems, which
Q38: In the design phase of the systems
Q39: In the design phase of the systems
Q40: During the _ phase of the systems
Q42: _ is a philosophy and a software
Q43: Which of the following approaches for developing
Q44: In _ conversion of the implementation phase
Q45: During the _ of the systems development
Q46: In _ conversion of the implementation phase
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents