What Is a Change Order

Question 5

Multiple Choice

What is a change order?


A) the document produced to describe a part of the job requirement that has been changed from what was originally bid
B) an invoice that is marked as "paid"
C) a contractor request for a change of personnel
D) another name for the invoice issued

Correct Answer: