A contractor and Southampton, Inc.have a contract, which calls for the contractor to build a building with the completion by June 15.If the building is not completed by that date, the contract calls for the contractor to pay $100 per day in damages.The $100 per day is:
A) liquidated damages.
B) an illegal penalty.
C) punitive damages.
D) nominal damages.
Correct Answer:
Verified
Q21: Even if a party has the power
Q22: If the parties to a contract stipulate
Q30: Gina contracts with Lonnie to build a
Q36: Restitution can be obtained where a voidable
Q41: What principle did the court apply in
Q43: Jimmy made a contract to sell his
Q44: A power of avoidance held by a
Q45: Arlene signs an employment contract to work
Q46: Which of the following is NOT true
Q47: Contract damages that put the injured party
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents