Holly has been tasked to design the plan the IT department will use when making a change to systems. The plan will be used anytime the company needs to change a system and should include which people are to be contacted when changes are made and what the changes will do to other equipment.
While Holly writes the change document, what types of things will she need to include in the scope of change? (Select all that apply.)
A) Key components of the change and how they will be addressed
B) Risk or problems that might arise during the change
C) Skill sets, tasks, and activities required to carry out the change
D) A plan in case something happens and the change cannot be executed
E) Who will participate in the change
F) How the success of the change will be measured
Correct Answer:
Verified
Q61: Peggy found a freely distributed software package
Q62: Nick works for a software development company
Q63: Jeff owns a health care company that
Q64: Your company has decided to replace several
Q65: Ken has discovered that a vice president
Q66: Jacob has discovered what he believes is
Q68: Joann turned on her Windows 10 computer
Q69: James has a USB flash drive that
Q70: During an upgrade for a new web
Q71: Which authentication service options work with Active
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents