A contractor and Southampton, Inc. have a contract, which calls for the contractor to build a building with the completion by June 15. If the building is not completed by that date, the contract calls for the contractor to pay $100 per day in damages. The $100 per day is:
A) punitive damages.
B) nominal damages.
C) liquidated damages.
D) an illegal penalty.
Correct Answer:
Verified
Q23: Miller made a contract to sell his
Q24: The purpose of reliance damages is to
Q25: Marcella pays $12,000 down on a houseboat
Q26: According to the "American Rule," when contracting
Q27: Arlene signs an employment contract to work
Q29: A small breach of contract damage amount
Q30: Even if a party has the power
Q31: The test of foreseeable damages is subjective.
Q32: Delay will have no effect on the
Q33: When a breach of contract occurs, the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents