Project Alpha has an NPV of $10 million and a standard deviation based on risk analysis of $3 million. Project Beta has an NPV of $8 million and a standard deviation based on risk of $2 million. Which project should be selected and why?
A) Select Alpha because it has the higher NPV.
B) Select Beta because it has the lower risk as represented by standard deviation.
C) Select either project because both have positive NPVs and relatively low risk compared to their NPVs.
D) Don't select either project because there is too much risk associated with both projects.
E) There is no clear decision rule, the choice depends on management's degree of risk aversion.
Correct Answer:
Verified
Q11: Decision tree analysis:
A)provides a relatively quick and
Q12: The NPV and IRR derived from estimated
Q13: Portfolio theory makes it possible to incorporate
Q14: Which of the following is not a
Q15: A real option that allows a company
Q17: Which of the following is not a
Q18: Which of the following is/are included in
Q19: Richmond Graphics is a small company contemplating
Q20: Scenario/sensitivity analysis is a procedure that can
Q21: Scenario analysis for a proposed new project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents