Nash, Inc. is looking at a 4-year project that will cost $4 million to initiate. Based on a range of economic forecasts, Nash has forecasted a worst case, best case and most likely case with respect to cash flows that this project will generate and assigned probabilities to these forecasts. The worst case forecast (30% probability)is $1.2 million per year. The best case (20% probability)is $1.8 million per year with an additional $1 million in the fourth year. The most likely forecast (50% probability)is $1.5 million per year with an additional $0.5 million in the fourth year. The cost of capital is 14%.
a. What is the NPV ($000)of the worst case scenario?
b. What is the NPV ($000)of the best case scenario?
c. What is the NPV ($000)of the most likely scenario?
d. What should Nash use to approximate the expected NPV ($000)of the project?
Correct Answer:
Verified
a. CFo = -4,000; C01 through C04...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q90: The following information is associated with a
Q91: Explain the certainty equivalent approach.
Q92: The pure play method of estimating risk
Q93: What is Monte Carlo simulation? How is
Q94: The certainty equivalent approach makes risky projects
Q96: If a capital budgeting project is a
Q97: The concept of risk aversion from portfolio
Q98: Why may an analysis that makes even
Q99: The certainty equivalent approach uses the cost
Q100: The certainty equivalent approach uses computer simulation
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents