Question 8

Multiple Choice

In the case of a shipbuilder engaged in a government contract which of the following would be the earliest point at which it would be reasonable to recognise revenue?


A) At the point the contract is signed
B) As payments on account are received
C) As invoices for work done are raised
D) When the work is complete and the ship has been delivered
E) When final payment is received