The Project Leader Usually Records ____ in a Project Plan

Question 16

Multiple Choice

The project leader usually records ____ in a project plan.


A) required activities and the order of activities
B) time estimates and cost estimates for each activity
C) activities that can take place at the same time
D) all of the above

Correct Answer: