Customer demand is 120 units per week. The company works on a 9-hour shift per day, 5-day per week basis. Each shift has a ½-hour lunch break and two 15-minute coffee breaks. The cycle time is 12 minutes. To meet demand, production must occur at the rate of one unit every:
A) 12 minutes.
B) 20 minutes.
C) 22.5 minutes.
D) 28 minutes.
Correct Answer:
Verified
Q162: Which of the following actions by trading
Q163: An operations manager wants to measure variability
Q164: The purchasing manager of a company wants
Q165: Which of the following metrics would be
Q166: A manufacturer has direct relationships with its
Q168: A company has adequate average available capacity
Q169: Point-of-sale information fails to measure actual demand
Q170: Which of the following benefits is most
Q171: A company exports products to emerging markets.
Q172: Variation in upstream requirements can be reduced
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents