Which of these are correct if Cpk Upper is 2.0 and Cpk Lower is 1.0?
A) The process is not stable.
B) The process is shifted to the left.
C) Cpk must be reported as 1.0.
D) The process Mean is 1.5.
Correct Answer:
Verified