Which of the following statements about quality assurance and Project Assurance is true?
A) Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
B) Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
C) Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
D) Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Correct Answer:
Verified
Q79: Which is a purpose of the Managing
Q80: Identify the missing words in the following
Q81: Which is NOT a recommended quality review
Q82: What process provides the information required to
Q83: Which role is part of the project
Q85: Which document should record the agreed amount
Q86: Which is a purpose of the Organization
Q87: Which is one of the three levels
Q88: During the Managing a Stage Boundary process,
Q89: What is the collective name for individuals
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents