Which describes a risk effect?
A) The uncertainty expressed as a negative or favourable occurrence
B) The issue which is affecting the project and has resulted in a risk
C) The impact(s) on the project objectives should the threat or opportunity occur
D) The change in the status of a risk in response to actions taken to control it
Correct Answer:
Verified
Q131: Identify the missing product in the following
Q132: Which of the following is NOT part
Q133: Which is NOT one of the levels
Q134: Why would the Project Manager escalate an
Q135: Identify the missing word(s) in the following
Q136: What theme estimates the cost of delivering
Q137: Which is NOT a true statement about
Q139: Which is a PRINCE2 time-driven control?
A) End
Q140: In which product would you find a
Q141: Which is the Change Authority role permitted
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents