Assume you are managing the system testing phase of a project. The system test execution period is scheduled to twenty weeks. All tests are manual tests. You are following a risk-driven test approach. During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests. Which of the following would you expect to be the best way to respond to this situation?
A) Prioritize executing the tests for the highest product risks and track these risks.
B) Remove testers from your test team, so that they can be assigned to other projects.
C) Automate all remaining tests.
D) No action is needed, test as much as possible in the remaining time period.
Correct Answer:
Verified
Q19: Consider a defect report and assume that
Q20: Which of the following statements about the
Q21: You can count on well-written requirements, but
Q22: Assume you are the Test Manager for
Q23: The following is the unique "critical" quality
Q25: The following is the unique "critical" quality
Q26: You are the Test Manager on a
Q27: Assume you are the Test Manager in
Q28: You are performing a quality risk analysis
Q29: Assume that the following test cases have
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents