The budget and actual cost statements for the production department for the latest period were as follows. 11ec37eb_8baf_8298_97b9_bbe728f13da1__00 Notes. The 10% increase in production was required to meet unexpected additional sales demand. The production manager is responsible for negotiating the price of materials with suppliers. The normal working time is 900 hours per period. Any overtime worked above these 900 hours is paid at a premium of 50%. In preparing the flexible budget for the latest period, which TWO of the following statements are correct? (Choose two.)


A) The fixed costs should be flexed to $40,000 + 10% = $44,000.
B) The material quantity should be flexed to 60,000 + 10% = 66,000 kg.
C) The basic pay hours should not be flexed; they should remain at 1,000 hours.
D) The overtime hours should be flexed to (1,000 + 10%) - 900 = 200 hours.
E) The material price should be flexed to the actual figure of $3.10 per kg.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents