When managing the critical path of an IT security project, which of the following is MOST important?
A) Knowing all the stakeholders.
B) Knowing the milestones and timelines of deliverables.
C) Knowing the people on the data center team.
D) Knowing the threats to the organization.
Correct Answer:
Verified