You are the business analyst for your organization and preparing to complete the requirements elicitation activities. Your manager wants to know when the requirements elicitation process will be completed. Which of the following responses best describes the nature of the requirements elicitation process?
A) The schedule of the project determines the duration of the requirements elicitation process .
B) The duration of the requirements elicitation activities is determined by the willingness of the project stakeholders to contribute to the requirements information.
C) The size of the project determines the duration of the requirements elicitation process.
D) Eliciting requirements is not a compartmentalized activity.
Correct Answer:
Verified
Q109: Which of the following is NOT a
Q110: Which of the following is a quality
Q111: What type of interview is the most
Q112: You are the business analyst for your
Q113: Marcy is the business analyst for her
Q115: You are the business analyst for the
Q116: What type of requirements elicitation technique is
Q117: You are the business analyst for your
Q118: Your organization is using a plan-driven approach
Q119: Which of the following meeting brings all
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents