Which of the following is a visual decomposition of the program scope and the resources needed in order to create the things defined within the program scope?
A) Resource breakdown structure (RBS)
B) product breakdown structure (PBS)
C) Budgeted Cost of Work Scheduled (BCWS)
D) Work Breakdown Structure (WBS)
Correct Answer:
Verified
Q116: What type of requirements elicitation technique is
Q117: You are the business analyst for your
Q118: Your organization is using a plan-driven approach
Q119: Which of the following meeting brings all
Q120: What requirements elicitation involves carefully selected stakeholders
Q122: Which of the following statements best describes
Q123: Henry is the business analyst for his
Q124: Which of the following authorizes the project
Q125: Which of the following graphical presentations of
Q126: Which of the following models demonstrates the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents