A Project's Change in Scope Is Assessed and a Newly

Question 172

Multiple Choice

A project's change in scope is assessed and a newly assigned business analyst (BA) is unsure how to communicate the findings and final decision to the wider stakeholder group. In which of the following can the BA find this information?


A) Stakeholder Communications Plan
B) Business case
C) Business policies
D) Governance approach

Correct Answer:

verifed

Verified