In Performing the Task of Planning for Business Analysis Governance

Question 163

Multiple Choice

In performing the task of planning for business analysis governance for a software implementation project, the business analyst (BA) recommends that prioritization of requirements be done based on the amount of work that the project team is capable of delivering in a given period of time. Which of the following techniques is the BA recommending?


A) Negotiation
B) Grouping
C) Time Boxing
D) Budgeting