A business analyst (BA) is working on improving solution performance and increasing value. The BA discovers that a set of interfaces and activities do not contribute to the final product either directly or indirectly. What should the BA recommend?
A) Provide a single solution for stakeholders thus reducing the cost of implementation
B) Remove or minimize interfaces and activities that do not provide value to the final product
C) Retire the current solution as it is not fulfilling the need for which it was created
D) Propose an organizational change to automate the work people perform
Correct Answer:
Verified
Q284: A company is about to embark upon
Q285: During a retrospective, the project team agrees
Q286: A business analyst (BA) is assessing the
Q287: Due to the complexity of a project,
Q288: A software company has won a contract
Q290: You are the business analyst for a
Q291: A business analyst (BA) was tasked with
Q292: A business analyst (BA) is assigned to
Q293: All of the following stakeholders participate in
Q294: A conservative company with rigorous risk control
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents