What element of the conduct elicitation activity is tracked to provide a basis for future planning?
A) Time actually spent eliciting the requirements
B) Number of stakeholders that did not participate in the requirements elicitation
C) Cost of actually eliciting the requirements
D) Changes that entered the scope throughout the requirements elicitation activities
Correct Answer:
Verified
Q360: Zoe is the business analyst for her
Q361: What is the purpose of the business
Q362: You are coaching Marcy, a new business
Q363: You are the business analyst for your
Q364: Which of the following models defines the
Q366: You are the business analyst for your
Q367: Jenni is the business analyst for the
Q368: What requirements elicitation technique examines the available
Q369: What does the T in SWOT analysis
Q370: You are the business analyst for your
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents