If inconsistencies arise between different elicitation results, the business analyst (BA) should:
A) escalate them to the business sponsor.
B) report them to the project manager.
C) resolve them through collaboration.
D) reconcile them through experience.
Correct Answer:
Verified
Q57: Which behavioural characteristic enables the business analyst
Q58: Which business analysis activity ensures that a
Q59: What is a valid reason for prioritization?
A)
Q60: What characterizes a good collaboration with stakeholders?
A)
Q61: What tool classifies stakeholders according to responsibility?
A)
Q63: Which of the following approaches is used
Q64: What is a logical data model used
Q65: Which action would a business analyst (BA)
Q66: What are matrices in modelling formats used
Q67: Who is responsible for discovering, synthesizing, and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents