While developing a risk based audit plan, which of the following sources of information would provide the least value to the chief audit executive?
A) Results from the organization's business process management program.
B) User acceptance testing of the organization's enterprise resource planning application.
C) Risk assessments conducted by the board.
D) Key business strategies adopted by the organization in the strategic plan.
Correct Answer:
Verified
Q218: According to IIA guidance, which of the
Q219: The chief executive officer has requested that
Q220: Which of the following would be the
Q221: Which of the following is not true
Q222: During a consulting engagement, an internal auditor
Q224: Which of the following is correct with
Q225: Which of the following would be included
Q226: An organization has an opening for an
Q227: According to the Standards, which of the
Q228: An organization decides to create an internal
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents