Which of the following would be carried out as part of a post-project benefits review?


A) An assessment of whether the project fulfilled its original objectives
B) A review of the performance of the project's products in operational use and identification of whether there have been any side-effects
C) An assessment of the project's risk management procedure
D) A review of the performance of the project management method and the project management team

Correct Answer: