Which of the following statements is CORRECT?
A) IT Service Continuity Management can only take place once Business Continuity Management has been established
B) Where Business Continuity Management is established, business continuity considerations should form the focus for IT Service Continuity Management
C) Business Continuity Management and IT Service Continuity Management must be established at the same time
D) IT Service Continuity Management is not required when IT is outsourced to a third party provider
Correct Answer:
Verified
Q232: Which process is responsible for controlling, recording
Q233: Which role is accountable for a specific
Q234: Configuration Management Databases (CMDBs) and the Configuration
Q235: What is most likely to cause a
Q236: What type of improvement should be achieved
Q238: When should tests for a new service
Q239: Which of the following is NOT a
Q240: Defining the processes needed to operate a
Q241: Which process lists "Understanding patterns of business
Q242: Which model delivers a view of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents