You are reviewing a new data center design for a customer. They chose to leverage a tunnel-based overlay technology for quick deployment and multitenant security. Which design concern can affect the availability across the data center?


A) nonoverlapping IP address space between the overlay networks
B) MTU size on the underlay links
C) proper placement of STP root bridge in overlay networks
D) review placement of STP root bridge in overlay networks