The element of the MRP record which is the quantity that has already been ordered and will be received at the beginning of the period is called
A) gross requirements.
B) net requirements.
C) scheduled receipts.
D) planned order receipts.
Correct Answer:
Verified
Q95: The system that is used to manage
Q96: The table below provides information about demand
Q97: The ratio of actual output to design
Q98: The ratio of actual output to actual
Q99: The capacity strategy where capacity is only
Q101: The process of time phasing and calculating
Q102: Demand that is calculated from the requirements
Q103: The feasibility check of a Materials Requirement
Q104: The element of the MRP record which
Q105: Demand that is calculated from the requirements