Including the Change Control System Within the ________ Is a Key

Question 33

Multiple Choice

Including the change control system within the ________ is a key to a successful project.


A) Work Breakdown Structure
B) Project Baseline
C) Risk Management Plan
D) Work Breakdown Structure and Project Baseline

Correct Answer:

verifed

Verified