Near the end of a Sprint, the team realizes that they will not be able to complete the stories they had committed to. What is the best course of action for the team?
A) Add resources and team members to meet the goals of the current Sprint.
B) Ask the Product Owner to decide which stories can be delayed until the next Sprint.
C) Decide on a new definition of 'done' for the Sprint Backlog Items.
Correct Answer:
Verified
Q8: The Product Owner is going on a
Q9: A large product team features six different
Q10: During the release planning meeting, it is
Q11: What is time-boxing?
A) A period of intense
Q12: How does Agile bring predictability to the
Q14: What is an "escaped defect"?
A) A defect
Q15: Who knows most about the progress towards
Q16: A user story was estimated at five
Q17: What is the usual length of the
Q18: A Project Manager wants to track not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents