The Product Owner is going on a three-week vacation. The team should be closing the current Sprint and starting a new Sprint at the end of the first week of the Product Owner's vacation. What is the best way to continue the Scrum rituals in this situation?
A) Each Scrum team should ideally have two Product Owners to provide cover.
B) The Product Owner should be requested to delay his vacation by a week.
C) The Scrum Master should take over and cover for the Product Owner.
Correct Answer:
Verified
Q3: How should 'done' be defined when multiple
Q4: What is the best way to split
Q5: When is a Sprint complete?
A) When all
Q6: What message can you give to a
Q7: What is a characteristic of a well-designed
Q9: A large product team features six different
Q10: During the release planning meeting, it is
Q11: What is time-boxing?
A) A period of intense
Q12: How does Agile bring predictability to the
Q13: Near the end of a Sprint, the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents